Project Client 2007 2010 semicolon separator issue

I have encounterd some issue when regional settings is set to german, for the Project Client. Basically the list separator for the german language is “;” (could be for other languages as well) instead of “,” and when someone tries to add ressources for a task he must enter usually “firstname ; lastname” Here is were…


Project Client 2010 integration with Sharepoint Task List

First upgrade to at least SP1 the project client because the Sync with task list has been upgraded in SP1 See: http://blogs.msdn.com/b/project/archive/2011/05/18/project-2010-sp1-enhancements-to-sync-to-sharepoint-task-list.aspx Second, add the field in Backstage – Manage fields. See: http://blogs.msdn.com/b/project/archive/2009/10/19/project-2010-introducing-sync-to-sharepoint.aspx http://www.microsoft.com/project/en-us/sync-sharepoint.aspx http://workerthread.wordpress.com/2010/06/01/sharepoint-2010-project-tasks-part-2-synchronise-with-project-2010/ A few important things to notice are: · Summary tasks are supported in the synchronization · Most custom fields can…

1