Project Client 2010 integration with Sharepoint Task List

First upgrade to at least SP1 the project client because the Sync with task list has been upgraded in SP1 See: http://blogs.msdn.com/b/project/archive/2011/05/18/project-2010-sp1-enhancements-to-sync-to-sharepoint-task-list.aspx Second, add the field in Backstage – Manage fields. See: http://blogs.msdn.com/b/project/archive/2009/10/19/project-2010-introducing-sync-to-sharepoint.aspx http://www.microsoft.com/project/en-us/sync-sharepoint.aspx http://workerthread.wordpress.com/2010/06/01/sharepoint-2010-project-tasks-part-2-synchronise-with-project-2010/ A few important things to notice are: · Summary tasks are supported in the synchronization · Most custom fields can…